Just Waitin...

Well, not too much to report. The concrete they poured for the footings need to sit for about a week before they pour the walls. So it'll be about next Tuesday or Wednesday before there are any new or interesting pictures to post. I did talk with the factory. They notified me that my house will be delivered on the 23rd. This is pretty good news. That date is good because the walls will have been poured and sitting for a week... enough time to harden/cure. According to all the framers I've spoken with, it should take at most two weeks to put everything together. Now I just got to pick a framer, a roofing contractor, and a siding contractor... soon. :)